City office, experts inspect Taipei Dome site

RESUMPTION? Farglory did not breach the law, as it had only moved an ice tank as part of court-approved remedial work and had not restarted construction, the group said

Taipei Times
Date: Jul 03, 2019
By: Lee I-chia  /  Staff reporter

The Taipei Construction Management Office and several technical associations yesterday held a

The Taipei Dome is pictured on June 18.
Photo: Chang Chia-ming, Taipei Times

joint inspection of the Taipei Dome construction site, following reports alleging that contractor Farglory Group has resumed construction work.

A local media outlet reported that it had been tipped off by a member of the public, who said that Farglory was installing an air-conditioning system at the site.

The Taipei City Government in May 2015 ordered that construction be halted because of unauthorized changes to approved blueprints.

In 2016, the Taipei High Administrative Court ruled that Farglory could continue 14 safety-related remedial tasks, including flood prevention and drainage system work, fire prevention, rust prevention and other work to prevent the structure from collapsing.    [FULL  STORY]